Project Timeline
Key milestones in the development, approval, and construction of the Aratina Solar Center.
Original PPA Announced
8minute Solar Energy (now Avantus) announces original Power Purchase Agreements with Monterey Bay Community Power and Silicon Valley Clean Energy.
Notice of Preparation
Official Notice of Preparation issued, initiating the environmental review process.
Environmental Authorization
California Department of Fish and Wildlife issues Take Authorization for Western Joshua Tree (effective Oct 29).
Planning Commission Hearing
Kern County Planning Commission reviews the project proposal and environmental impact report.
Project Approval
Kern County Board of Supervisors unanimously approves the Aratina Solar Project.
Construction Financing Secured
Avantus closes over $500 million in construction financing for Aratina 1.
Aratina 2 PPA Announced
Avantus signs 15-year Power Purchase Agreements with Southern California Edison for Aratina 2.
Tax Equity Investment
$300 million tax equity investment secured for Aratina 1.
Commercial Operations
Aratina 1 and Aratina 2 expected to begin commercial operations, delivering clean energy to the grid.
Looking Ahead
The Aratina Solar Center is designed for a long operational life, providing clean, reliable energy and economic benefits to Kern County for decades to come.